Fairhope, Alabama.
PERIMETER TRAIL ADDED
The city council has passed a resolution applying for a new federal grant to construct a (non-motorized) asphalt walking path around the perimeter of the Soccer Complex now under construction on Manley Rd/CR13.
The grant was announced in June and pre-application had to be made by July 31st for the city's "highest priority" trail project -- according to Recreation Trails Program (RTP) stipulations.
The trail will cost an estimated $125K, but the grant is for only $100K with a 20% match; the city will have to come up with an additional $45K of its own money -- if it is ultimately approved by the governing state agency, ADECA.
COMPLEX TAKING SHAPE
Most of the extensive earth-moving work to level the playing fields (the project's most costly phase) appears to have been completed; the green mounds of dirt are topsoil to be re-used for the fields themselves.
Also, police say there has been some trouble with motorcycles and off-road vehicles damaging terrain on the construction site.
Completion should be in time for Spring tournaments.
PERIMETER TRAIL ADDED
Manley Soccer complex |
The city council has passed a resolution applying for a new federal grant to construct a (non-motorized) asphalt walking path around the perimeter of the Soccer Complex now under construction on Manley Rd/CR13.
The grant was announced in June and pre-application had to be made by July 31st for the city's "highest priority" trail project -- according to Recreation Trails Program (RTP) stipulations.
The trail will cost an estimated $125K, but the grant is for only $100K with a 20% match; the city will have to come up with an additional $45K of its own money -- if it is ultimately approved by the governing state agency, ADECA.
COMPLEX TAKING SHAPE
Most of the extensive earth-moving work to level the playing fields (the project's most costly phase) appears to have been completed; the green mounds of dirt are topsoil to be re-used for the fields themselves.
Also, police say there has been some trouble with motorcycles and off-road vehicles damaging terrain on the construction site.
Completion should be in time for Spring tournaments.
proposed perimeter walking trail |
original plan. cr 13 to left |