Update: Construction will not be completed by Labor Day, as was hoped for.
COMPLETED THIS WEEK ?
Sod is being installed in the center of the new roundabout and final paving work should begin this later week, according to city engineer Johnson.
Hopefully the paving can done overnight to minimize disruption to traffic -- or on Saturday, he said.
Then, temporary striping will be applied until the new asphalt has time to cure, so the final permanent paint may be applied.
Asphalt Services is the prime contractor.