Water Tower Painting Progress Report

Fairhope, Alabama

UPDATE: THIS PROJECT BEGAN LAST DECEMBER BUT SOON FELL BEHIND SCHEDULE DUE TO MANPOWER SHORTAGE ISSUES, THEY SAID.  IT SHOULD HAVE BEEN COMPLETED LAST MONTH. (CLICK)







STILL BEHIND SCHEDULE

Work has begun on the exterior of the 2 million gallon water tank on Fairhope Avenue but completion is not expected any time soon; additional workers were hired to expedite completion.

The interior of the tank is not completed yet either.

$200/day penalties were imposed on the contractor for the delay, who did not complete the project in the 180 days allowed by the contract.